Geotechnical Works Guernsey
Work Carried out: Soil Nailing, Gunite application Client: Crocker Civil Engineering
CAS Ltd were subcontracted to Crocker Civil Engineering to carry out slope stabilisation works at Juas Quarry, Guernsey
The work involved drilling over 100 Nr. 25mm diameter Dywidag Hollow Mai Bar Soil Nails between 8 to 10 metre penetration depths and grouting, 30 Nr. Rock Anchors and associated Geotextile Fabric, Mesh Reinforcement and Concrete Gunite over the entire surface. 
|